1. Meetings with client (Sarah - 10 hrs/$200)
1.1. Initial Meeting (Sarah 5 hrs/$100)
1.1.1. Determine initial requirements and add-on requests. (Cement Pad, Fence, Insulation, ect) (Jason - 1 hr)
1.1.2. Finalize a Budget (Sarah - 3 hrs)
1.1.3. Timeline requirements (Sarah - 1 hr)
1.2. Middle Progress Meeting (Sarah - 3 hrs/$60)
1.2.1. Review Blueprints (Jason - 1 hr)
1.2.2. Update on estimated time to completion (Sarah - 1 hr)
1.2.3. Approval of Blueprints (Sarah - 1 hr)
1.3. Final Progress Meeting (Sarah - 2 hrs/$40)
1.3.1. Final Approval (Jason - 1 hr)
1.3.2. Get Paid (Sarah - 1 hr)
2. Pre-Construction Material and Supply Tasks (Jason - 9 hrs/$180)
2.1. Initial Purchasing and Supplies (Jason 6 hrs/$120)
2.1.1. Purchase framing wood (Jason - 1 hr)
2.1.2. Purchase Paint (Sarah - 1 hr)
2.1.3. Purchase Shingles (Jason - 1 hr)
2.1.4. Purchase Cement (Jason - 1 hr)
2.1.5. Purchase Insulation (Jason - 1 hr)
2.1.6. Purchase/Rent Tools (Jason - 1 hr)
2.2. Delivery Schedules (Jason - 3 hrs/$60)
2.2.1. Schedule delivery of supplies Jason - 1 hr)
2.2.2. Schedule cement delivery to site (Sarah - 1 hr)
2.2.3. Schedule transportation of dog house from factory to site (Jason - 1 hr)
3. Design (Sarah - 8 hrs/$160)
3.1. On site measurements (Sarah - 3 hrs/$60)
3.1.1. Measure site area for dog house (Sarah - 2 hrs)
3.1.2. Measure Fluffy (Sarah - 1 hr)
3.2. Creating Blueprint (Sarah - 5 hrs/$100)
3.2.1. Design Walls (Jason - 1 hr)
3.2.2. Design Roof (Jason - 1 hr)
3.2.3. Design door (Sarah - 1 hr)
3.2.4. Design cement pad (Sarah - 2 hrs)
4. Construction (Jason - 25 hrs/$500)
4.1. Roof Construction (Jason - 4 hrs/$80)
4.1.1. Frame roof (Jason - 2 hrs)
4.1.2. Insulate roof (Jason - 1 hr)
4.1.3. Apply shingles to roof (Sarah - 1 hr)
4.2. Wall Construction (Jason - 6 hrs/$120)
4.2.1. Frame walls (Jason - 1 hr)
4.2.2. Create door in front wall (Jason - 1 hr)
4.2.3. Insulate walls (Jason - 1 hr)
4.2.4. Paint walls (Jason - 1 hr)
4.2.5. Create any windows if requested (Jason - 2 hrs)
4.3. Cement Pad Construction (Jason - 11 hrs/$220)
4.3.1. Dig hole for concrete (Jason - 4 hrs)
4.3.2. Frame area for pouring of concrete (Jason - 2 hrs)
4.3.3. Delivery/Spreading of Concrete (Jason - 4 hrs)
4.3.4. Allow for Fluffy's paw print in concrete before drying (Sarah - 1 hr)
4.4. Finishing Construction (Jason - 4 hrs/$80)
4.4.1. Connect roof to walls (Jason - 1 hr)
4.4.2. Touchup painting in any areas (Sarah - 2 hrs)
4.4.3. Install any extras (Jason - 1 hr)