1. Technology Stream
1.1. 145 Optimisation Strategy
1.1.1. ROBIN
1.1.1.1. System Requriements
1.1.1.2. Deployment
1.1.1.2.1. Sydney
1.1.1.2.2. Brisbane
1.1.1.2.3. Change management
1.1.2. Laptop
1.1.2.1. Distribution Rules
1.1.2.2. Desktop / Laptop Integration
1.1.2.2.1. Docking Stations
1.1.2.2.2. Keyboards
1.1.2.2.3. Mouse
1.1.2.2.4. External Camera
1.1.3. Audio Visual
1.1.3.1. Will electrical services engineer assist with scope for 145?
1.1.3.1.1. If not, how do we align requirements? Vendor selected
1.1.4. Protoyping
1.1.4.1. Space Requirement
1.1.5. Teams
1.1.5.1. Audio Visual
1.1.5.2. Telephony
1.1.6. Headset
1.1.6.1. who governs how this is done
1.1.6.1.1. ICT
1.1.6.1.2. SP
1.1.6.1.3. Change Management
1.1.7. Strategy for re-use of workstation hardware
1.1.7.1. redeploy into 300 George Street
1.1.7.1.1. consisitency across fitout
1.1.7.2. Disposal
1.1.7.3. Donation
1.1.7.3.1. wiping hardware considerations
1.2. 300 George
1.2.1. ICT Infrastructure Planning
1.2.1.1. Network
1.2.1.2. Systems
1.2.1.3. Architecture
1.2.1.4. WAN - Fixed Services
1.2.1.5. Transition Planning - 145 Ann Street to 300 George Street
1.2.1.6. Space Requirements at 300 George Street
2. Construction Stream
2.1. Concept Design 31/05/21- 25/06/21
2.1.1. Electrical Services Engineer
2.1.1.1. GSB IT standards and processes