1. Buy Materials (Brennan 6 Hours $500 + price of material)
1.1. Contact Concrete Company (1 Hour)
1.1.1. Get estimate on job
1.1.1.1. Schedule a time for concrete
1.2. Wood (1 hour)
1.2.1. Buy enough wood
1.2.1.1. Correct type of wood
1.3. Insulation (1 Hour)
1.3.1. Purchase enough for whole house
1.4. Windows (1 Hour)
1.4.1. Measure size of frame
1.4.1.1. Correct window size
1.4.1.1.1. Durable
1.5. Door/Door Flap (1 Hour)
1.5.1. Measure door frame
1.5.1.1. Correct size
1.6. Food/Water bowl (1 Hour)
2. Design (Brennan 6 hours) $500
2.1. Create blueprint (3 Hours)
2.2. Measure the area (1 Hour)
2.3. Location of the house
2.3.1. Scout the land around the house
2.3.1.1. Discuss with cusotmer where house will be located
2.4. Approve design with the customer (1 Hour)
2.4.1. Make need changes to the model
2.4.1.1. Agree on final design
3. Pricing (Aidan)
3.1. Estimated price of materials (1 Hour)
3.1.1. Get recipes from all purchases
3.2. Labor costs (1 Hour)
3.2.1. Keep track of hours and work done
3.3. Price of concrete/electric (1 Hour)
3.3.1. Keep document of estimates and invoice from rom concrete
3.3.1.1. Keep document of estimates and invoice from rom electric
3.4. Insurance (1 Hour)
3.5. Contract (2 Hours)
3.5.1. Finalize contract with customer and other employees
4. Construction (Aidan 2 days) $1500
4.1. Pour Concrete (4 Hours) $1000
4.1.1. Dig foundation (2 Hours)
4.1.1.1. Mix concrete (1 hour)
4.1.1.1.1. Finish and touch up (1 Hour)
4.2. Contact electric (1 Hour)
4.2.1. Get an estimate for electric
4.2.1.1. Have electrician complete neccesary electric for dog house (2 Hours) $200
4.3. Build frame (3 Hours) $100
4.4. Insualte (2 Hours) $40
4.4.1. Put walls over insullation