AET - WBS

Get Started. It's Free
or sign up with your email address
AET - WBS by Mind Map: AET - WBS

1. General Contracting

1.1. Hire New Employees

1.1.1. Screen and Hire qualified laborers (7 Days)

1.2. Construction

1.2.1. Install new ventilation system (7 Days)

1.2.2. Install new racks (21 Days)

1.2.2.1. Run data cables (7 Days)

1.2.2.1.1. Install Power Supplies (5 Days)

2. Network Design

2.1. Scope and Design Network (14 days)

3. Operations

3.1. Fulfillment (total time for delivery - 3 weeks)

3.1.1. Order New Ventilation System (3 weeks for delivery)

3.1.2. Order New Racks (2 weeks for delivery)

3.1.3. Order Power Supplies (1 week for delivery)

3.2. Inspections

3.2.1. Inspections needed to approve construction (1 day)

3.3. Functioanal leadership meetings for "Switch Over" Approval

3.3.1. Operations Meeting (7 days)

3.3.2. Systems Meeting (7 days)

3.3.3. Facilities Meeting (7 Days)

3.3.4. Applications Meeting (7 Days)