Fruitland Baseball Skills Clinic 96 by Mind Map: Fruitland Baseball Skills Clinic 96

1. 2 Pamphlets 18 hr (Scott)

1.1. 2.1 Parent Pamphlet 9 hr (Allison)

1.1.1. 2.1.1 information gathering 3 hr (Will)

1.1.2. 2.1.2 Pamphlet 3 hr (Allison)

1.1.3. 2.1.3 Pamphlet Distribute 3 hr (Allison)

1.2. 2.2 Volunteer Pamphlet 9 hr (Scott)

1.2.1. 2.2.1 Information gathering 3 hr (Will)

1.2.2. 2.2.2 volunteer pamphlet 3 hr (Scott)

1.2.3. 2.2.3 volunteer pamphlet distribute 3 hr (Scott)

2. 4 Schedule 4 hr (Will)

2.1. 4.1 List of activities 2 hr (Will)

2.1.1. 4.1.1list of activities that will be performed at the clinic 2 hr (Will)

2.2. 4.2 Schedule of activities 2 hr (Will)

2.2.1. 4.2.1 list of activities 2 hr (Will)

3. 3 Materials 6 hr (Will)

3.1. 3.1 Equipment Check 6 hr (Will)

3.1.1. 3.1.1 Equipement 3 hr (Will)

3.1.2. 3.1.2 Water 3 hr (Will)

4. 5 Clinic 13 hr (Allison)

4.1. 5.1 Set Up 6 hr (Allison)

4.1.1. 5.1.1 Arrival of Volunteers 1 hr (Scott)

4.1.2. 5.1.2 Volunteer meeting 1 hr (Allison)

4.1.3. 5.1.3 Field Preparation 3 hr (Scott)

4.1.4. 5.1.4 Prepare for camper arrival 1 hr (Allison)

4.2. 5.2 Sign In 3 hr (Adam)

4.2.1. 5.2.1 Waiver forms 1 hr (Adam)

4.2.2. 5.2.2 important information 1 hr (Adam)

4.2.3. 5.2.3 camper sign in 1 hr (Adam)

4.3. 5.3 Clinic 3 hr (Will)

4.3.1. 5.3.1 scheduled activities 3 hr (Will)

4.4. 5.4 Check out 1 hr (Allison)

5. Survey 11 hrs (Adam)

5.1. 6.1 Parent + Kid Survey 5 hrs (Adam)

5.1.1. 6.1.1 survey the parents and attendees 4 hrs (Adam)

5.1.2. 6.1.2 Email 2 hr (Will)

5.1.3. 6.1.3 result analysis 4 hrs (Adam)

6. 1 Project Planning 38 hr (Will)

6.1. 1.1 Project Plan 16 hr (Allison)

6.1.1. 1.1.1 Work Breakdown Structure 4 hr (Allison)

6.1.2. 1.1.2 Responsibility Assignment 4 hr (Allison)

6.1.3. 1.1.3 Network Diagram 4 hr (Allison)

6.1.4. 1.1.4 baseline budget 4 hr (Adam)

6.2. 1.2 Project Charter 22 hr (Will)

6.2.1. 1.2.1 project timeline 4 hr (Will)

6.2.2. 1.2.2 Scope Statement 2 hr (Will)

6.2.3. 1.2.3 Stakeholders 2 hr (Scott)

6.2.4. 1.2.4 Success Criteria 2 hr (Scott)

6.2.5. 1.2.5 list of deliverable and milestones 4 hr (Scott)

6.2.6. 1.2.6 key assumptions, constraints, and major risks 2 hr (Will)

6.2.7. 1.2.7 project approval 6 hr (Will)

7. 7 Presentation 9 hrs (Scott)

7.1. 7.1 Hold Presentation 8 hrs (Scott)

7.1.1. 7.1.1 Clinic presentation. 8 hrs (Scott)

7.1.2. 7.1.2 Presenation 1 hr (Scott)