Planet Service создатель Mind Map: Planet Service

1. Connect the nodes from the old mini switch to a new IDF17 switch

2. Network equipment migration

2.1. Validation of F.O.

2.1.1. Old Site

2.1.1.1. Validate How many Fiber lines are available from this point to the New site.

2.1.1.2. Testing

2.1.1.3. Documentation of the tests.

2.1.2. IDF03

2.1.2.1. Validate How many Fiber lines are available from this point to the New site.

2.1.2.2. Testing

2.1.3. Documentation of the tests.

2.1.4. IDF05

2.1.4.1. Validate How many Fiber lines are available from this point to the New site.

2.1.4.2. Testing

2.1.4.3. Documentation of the tests.

2.1.5. Preparatives

2.1.5.1. Have equipment to make fiber connection in the event that on that day an event occurs due to problems of the tips.

2.2. Installing and tags ports

2.2.1. Core Switch

2.2.1.1. Tag the ports used in both Core Switches

2.2.1.2. Documentation of all the nodes used in this equipment

2.2.1.3. Documentation audit by Coordinator and Sub Manager

2.2.1.4. Move the device to the new Site

2.2.1.5. Connect Fibers and ports to the same ones that were previously connected

2.2.2. Merakis

2.2.2.1. Tag the ports used in both Merakis

2.2.2.2. Documentation of all the nodes used in this equipment

2.2.2.3. Documentation audit by Coordinator and Sub Manager

2.2.2.4. Move the device to the new Site

2.2.2.5. Connect cables ports to the same ones that were previously connected

2.2.3. IDF01

2.2.3.1. Tag the ports used

2.2.3.2. Documentation of all the nodes used in this equipment

2.2.3.3. Documentation audit by Coordinator and Sub Manager

2.2.3.4. Install New Switch (IDF17)

2.2.3.4.1. Connect Stacking module

2.2.3.5. Connect Fibers and Gibics

2.2.4. IDF SMT

2.2.4.1. Instalar Nuevo Switch

2.2.4.1.1. Connect Stacking module

2.2.4.1.2. Connect the nodes from the old mini switch to a new IDF17 switch

2.2.4.2. Tag the ports used

2.2.4.3. Documentation of all the nodes used in this equipment

2.2.4.4. Documentation audit by Coordinator and Sub Manager

2.2.4.5. Connect Fibers and Gibics

2.2.5. IDF03

2.2.5.1. Install new Switch (IDF15)

2.2.5.1.1. Connect Stacking module

2.2.5.1.2. Connect the nodes from the old mini switch to a new IDF17 switch

2.2.5.2. Tag the ports used

2.2.5.3. Documentation of all the nodes used in this equipment

2.2.5.4. Documentation audit by Coordinator and Sub Manager

2.2.5.5. Connect Fibers and Gibics