PMP - Values
저자: Éric Hervé
1. Bases
1.1. BAC = Budget at completion
1.2. AC = Actual cost
2. Values
2.1. EV = Earned % * BAC
2.2. PV = Planned % * BAC
3. Variances
3.1. CV = EV - AC
3.2. SV = EV - PV
4. Ratio
4.1. CPI = EV / AC
4.2. SPI = EV / PV
5. At completion
5.1. EAC = BAC / CPI
5.2. ETC = EAC - AC
5.3. VAC = BAC - AC
5.4. TCPI = (BAC-EV) / remaining funds
6. Present values
6.1. PV = FV / (1+i)ˆt
6.2. NPV = ∑ PV(t) - Initial investment
7. Returns
7.1. ROI = (Benefit - Cost) / Cost
7.2. ROIC = Net income after tax / capital invested
8. Expected monetary value
8.1. EMV = % * I
9. Channels
9.1. Ch = n * (n-1) / 2
10. Slacks
10.1. EF = ES + d - 1
10.2. LF = LS + d - 1
10.3. F = LS - ES
10.4. F = LF - EF