PMP - Values создатель Mind Map: PMP - Values

1. Bases

1.1. BAC = Budget at completion

1.2. AC = Actual cost

2. Values

2.1. EV = Earned % * BAC

2.2. PV = Planned % * BAC

3. Variances

3.1. CV = EV - AC

3.2. SV = EV - PV

4. Ratio

4.1. CPI = EV / AC

4.2. SPI = EV / PV

5. At completion

5.1. EAC = BAC / CPI

5.2. ETC = EAC - AC

5.3. VAC = BAC - AC

5.4. TCPI = (BAC-EV) / remaining funds

6. Present values

6.1. PV = FV / (1+i)ˆt

6.2. NPV = ∑ PV(t) - Initial investment

7. Returns

7.1. ROI = (Benefit - Cost) / Cost

7.2. ROIC = Net income after tax / capital invested

8. Expected monetary value

8.1. EMV = % * I

9. Channels

9.1. Ch = n * (n-1) / 2

10. Slacks

10.1. EF = ES + d - 1

10.2. LF = LS + d - 1

10.3. F = LS - ES

10.4. F = LF - EF