Начать. Это бесплатно
или регистрация c помощью Вашего email-адреса
Duketon Hydrogeology Appraisal создатель Mind Map: Duketon Hydrogeology Appraisal

1. Operations

1.1. DNO

1.1.1. Moolart Well

1.1.1.1. Mining

1.1.1.1.1. Buckingham

1.1.1.1.2. Blenheim

1.1.1.2. TSF

1.1.1.2.1. TSF3

1.1.2. Dogbolter/Coopers

1.1.2.1. Mining

1.1.2.1.1. Water storage development

1.1.3. Gloster

1.1.3.1. Mining

1.1.4. Petra

1.1.4.1. Ceased

1.2. DSO

1.2.1. Garden Well

1.2.1.1. Mining

1.2.1.1.1. Open Pit

1.2.1.1.2. Underground

1.2.1.2. TSF

1.2.1.2.1. TSF3

1.2.2. Rosemont

1.2.2.1. Mining

1.2.2.1.1. Open Pit

1.2.2.1.2. Underground

1.2.3. Tooheys Well

1.2.3.1. Mining

1.2.4. Baneygo/Idaho

1.2.4.1. Mining

1.2.5. Erlistoun

1.2.5.1. Ceased

1.2.6. Ben Hur

1.2.6.1. Mining

1.2.6.1.1. Hydrogeological Review

2. Colour Legend

3. Works proposed

4. Operations ceased

5. Works not proposed

6. PO Issued

7. Colour Legend

8. Completed works

9. Proposed works

10. Project Development: i) Regis ii) DMIRS iii) DWER

10.1. Priority 1

10.1.1. Ben Hur

10.1.1.1. Desk-based investigation

10.1.1.1.1. HAR

10.1.1.2. Site-based investigation

10.1.1.2.1. Phase 1

10.1.1.2.2. Phase 2

10.1.1.2.3. Phase 3

10.1.1.2.4. Phase 4

10.1.1.3. Analysis

10.1.1.3.1. Groundwater Model (SS)

10.1.1.3.2. Licensing

10.1.1.4. Operational recommendations

10.1.1.4.1. Permanent water distribution infrastructure

10.1.1.4.2. Horizontal drilling

10.1.1.4.3. In-pit water distribution infrastructure

10.1.2. Russell's Find

10.1.2.1. Desk-based investigation

10.1.2.1.1. HAR

10.1.2.2. Site-based investigation

10.1.2.2.1. Phase 1

10.1.2.2.2. Phase 2

10.1.2.2.3. Phase 3

10.1.2.2.4. Phase 4

10.1.2.3. Analysis

10.1.2.3.1. Groundwater Model (SS)

10.1.2.3.2. Groundwater Model (TR)

10.1.2.3.3. Licensing

10.1.2.4. Operational recommendations

10.1.2.4.1. Permanent water distribution infrastructure

10.1.2.4.2. Horizontal drilling

10.1.2.4.3. In-pit water distribution infrastructure

10.2. Priority 2

10.2.1. King Of Creation

10.2.1.1. Desk-based investigation

10.2.1.1.1. HAR

10.2.1.2. Site-based investigation

10.2.1.2.1. Phase 1

10.2.1.2.2. Phase 2

10.2.1.2.3. Phase 3

10.2.1.2.4. Phase 4

10.2.1.3. Analysis

10.2.1.3.1. Groundwater Model (SS)

10.2.1.3.2. Groundwater Model (TR)

10.2.1.3.3. Licensing

10.2.1.4. Operational recommendations

10.2.1.4.1. Permanent water distribution infrastructure

10.2.1.4.2. Horizontal drilling

10.2.1.4.3. In-pit water distribution infrastructure

10.2.2. Reichelt's Find

10.2.2.1. Desk-based investigation

10.2.2.1.1. HAR

10.2.2.2. Site-based investigation

10.2.2.2.1. Phase 1

10.2.2.2.2. Phase 2

10.2.2.2.3. Phase 3

10.2.2.2.4. Phase 4

10.2.2.3. Analysis

10.2.2.3.1. Groundwater Model (SS)

10.2.2.3.2. Groundwater Model (TR)

10.2.2.3.3. Licensing

10.2.2.4. Operational recommendations

10.2.2.4.1. Permanent water distribution infrastructure

10.2.2.4.2. Horizontal drilling

10.2.2.4.3. In-pit water distribution infrastructure

10.2.3. Commonwealth

10.2.3.1. Desk-based investigation

10.2.3.1.1. HAR

10.2.3.2. Site-based investigation

10.2.3.2.1. Phase 1

10.2.3.2.2. Phase 2

10.2.3.2.3. Phase 3

10.2.3.2.4. Phase 4

10.2.3.3. Analysis

10.2.3.3.1. Groundwater Model (SS)

10.2.3.3.2. Groundwater Model (TR)

10.2.3.3.3. Licensing

10.2.3.4. Operational recommendations

10.2.3.4.1. Permanent water distribution infrastructure

10.2.3.4.2. Horizontal drilling

10.2.3.4.3. In-pit water distribution infrastructure

10.3. Priority 3

10.3.1. Ventnor

10.3.1.1. Desk-based investigation

10.3.1.1.1. HAR

10.3.1.2. Site based investigation

10.3.1.2.1. HAR to inform

10.3.1.3. Analysis

10.3.1.3.1. HAR to inform

10.3.1.4. Operations

10.3.1.4.1. HAR to inform

10.3.2. King John

10.3.2.1. Desk-based investigation

10.3.2.1.1. HAR

10.3.2.2. Site based investigation

10.3.2.2.1. HAR to inform

10.3.2.3. Analysis

10.3.2.3.1. HAR to inform

10.3.2.4. Operations

10.3.2.4.1. HAR to inform

10.3.3. Davies Bore

10.3.3.1. Desk-based investigation

10.3.3.1.1. HAR

10.3.3.2. Site based investigation

10.3.3.2.1. HAR to inform

10.3.3.3. Analysis

10.3.3.3.1. HAR to inform

10.3.3.4. Operations

10.3.3.4.1. HAR to inform

10.4. Priority 4

10.4.1. Thompsons Bore

10.4.1.1. Desk-based investigation

10.4.1.1.1. HAR

10.4.1.2. Site based investigation

10.4.1.2.1. HAR to inform

10.4.1.3. Analysis

10.4.1.3.1. HAR to inform

10.4.1.4. Operations

10.4.1.4.1. HAR to inform

10.4.2. Terminator

10.4.2.1. Desk-based investigation

10.4.2.1.1. HAR

10.4.2.2. Site based investigation

10.4.2.2.1. HAR to inform

10.4.2.3. Analysis

10.4.2.3.1. HAR to inform

10.4.2.4. Operations

10.4.2.4.1. HAR to inform

10.4.3. Betelgeuse

10.4.3.1. Desk-based investigation

10.4.3.1.1. HAR

10.4.3.2. Site based investigation

10.4.3.2.1. HAR to inform

10.4.3.3. Analysis

10.4.3.3.1. HAR to inform

10.4.3.4. Operations

10.4.3.4.1. HAR to inform

11. Ongoing works

12. Duketon-wide

12.1. Data management (CHDMS)

12.1.1. Spatial data

12.1.1.1. Esri solutions (GIS solutions)

12.1.1.1.1. ArcGIS Desktop

12.1.1.1.2. ArcGIS Online Portal

12.1.1.1.3. ArcGIS Mobile

12.1.2. Non-spatial data

12.1.2.1. Database

12.1.2.1.1. Water levels

12.1.2.1.2. Water chemistry

12.1.2.1.3. Water flow rates

12.1.2.1.4. Infrastructure

12.1.2.1.5. Geology

12.1.3. Project-wide insights

12.1.3.1. Web app(s)

12.1.3.1.1. Hydrological/hydraulic

12.1.3.1.2. Hydrogeological

12.1.3.1.3. Land deformation

12.1.3.2. Specific deliverables

12.1.3.2.1. Reporting

12.1.3.2.2. Mine scheduling

12.2. Hydraulic Model

12.2.1. Inputs

12.2.1.1. Pump(s)

12.2.1.1.1. Pump performance curves

12.2.1.1.2. Dynamic head

12.2.1.2. Pipeline(s)

12.2.1.2.1. Dynamic head

12.2.1.3. Pond(s)

12.2.1.3.1. Capacity

12.2.2. Processes

12.2.2.1. Design

12.2.2.2. Pump specifications

12.2.2.3. Pipe specifications

12.2.3. Insights

12.2.3.1. Theoretical vs reality

12.2.3.2. System performance

12.2.3.3. Pumping efficiencies

12.3. Water Balance Model

12.3.1. Inputs

12.3.1.1. Flow rates

12.3.1.1.1. Hydraulic Model (current status)

12.3.1.1.2. Predicted (long-term)

12.3.1.2. Water usage

12.3.1.2.1. Hydraulic Model (current status)

12.3.1.2.2. Predicted (long-term)

12.3.2. Processes

12.3.2.1. LoM Schedule

12.3.2.2. Hydraulic Model

12.3.3. Insights

12.3.3.1. Annual Update Report

12.3.3.1.1. Infrastructure requirements

12.3.3.1.2. Water-use Strategy

12.3.3.2. Current status updates

12.3.3.2.1. 3MS

12.3.3.2.2. PMP

12.4. DWER/DMIRS

12.4.1. Regulatory Reports

12.4.1.1. Annual Groundwater Reports

12.4.2. Applications

12.4.2.1. Works Approval (if required)

12.4.2.2. Environmental License amendments

12.4.2.3. Water Licensing

12.4.2.4. Mining proposal

13. Colour Legend

14. Groundwater Model (TR)

14.1. Data requirements

14.1.1. Baseline water levels

14.1.1.1. Calibration

14.1.2. SS baseline results

14.1.3. Pump test data

14.1.4. Dewatering schedule

14.1.5. Pit shell design (per mining stage)

14.2. Processing abilities

14.2.1. Permeability & storage

14.3. Insights

14.3.1. Dewatering groundwater flow vector

14.3.2. Transient simulation (over LoM)

14.3.3. Groundwater transient dewatering simulation (over LoM)

14.3.4. Groundwater mass balance