1. Floor (Joe 13 hrs)
1.1. floor boards - Joe - 4 hrs
1.1.1. buy floor boards - Joe - 1 hr
1.1.2. stain floor boards - Joe - 1 hr
1.1.3. install floor boards - Joe - 2 hr
1.2. Dog Bed - Billy - 2 hours
1.2.1. buy dog bed - Billy - 1 hr
1.2.2. place dog bed inside house - Billy - 1 hr
1.3. framing - Joe - 7 hrs
1.3.1. make blueprints for floor - Joe - 2 hrs
1.3.2. build framing for floor - Joe - 2 hrs
1.3.3. put down framing for floor - Joe - 3 hrs
2. Walls (Billy 12 hrs)
2.1. insulation - Billy - 2 hr
2.1.1. buy insulation - Joe - 1 hr
2.1.2. put up insulation - Billy - 1 hr
2.2. flat screen tv - Joe - 4 hrs
2.2.1. buy TV - Joe - 1 hr
2.2.2. hang TV - Joe - 1 hr
2.2.3. setup the cable - Joe - 2 hr
2.3. framing - Billy - 6 hrs
2.3.1. make blueprints for walls - Billy - 2 hrs
2.3.2. build framing - Billy - 3 hrs
2.3.3. put up the framing - Joe - 1 hr
3. Roof (Billy 16 hrs)
3.1. shingles - Billy - 4 hrs
3.1.1. buy shingles - Billy - 1 hr
3.1.2. nail down shingles - Billy - 3hr
3.2. tyvek - Joe - 5 hrs
3.2.1. buy tyvek - Joe - 1 hr
3.2.2. apply tyvek to shingles - Joe - 4 hr
3.3. framing - Billy - 7 hrs
3.3.1. make blueprints for roof - Billy - 1 hr
3.3.2. build framing for roof - Billy - 3 hr
3.3.3. put up framing for roof - Billy - 3 hr
4. Door (Joe 14 hrs)
4.1. plastic door flap thingy - Joe - 3 hrs
4.1.1. buy plastic door flap thingy - Joe - 1 hr
4.1.2. install plastic door flap thingy - Joe - 2 hr
4.2. framing - Billy - 6 hrs
4.2.1. make blueprints for door - Billy - 1 hr
4.2.2. build framing for door - Billy - 3 hr
4.2.3. put up framing for door - Billy - 2 hr
4.3. door bell - Joe - 5 hrs
4.3.1. buy door bell - Joe - 1 hr
4.3.2. mount door bell - Joe - 1hr
4.3.3. wire door bell - Joe - 2 hr
4.3.4. test door bell - Joe - 1 hr
5. Tools & Materials (Billy 12 hrs)
5.1. Tools - Joe - 5 hrs
5.1.1. buy hammer - Joe - 1 hr
5.1.2. buy saw - Joe - 1 hr
5.1.3. buy tape measure - Joe - 1 hr
5.1.4. buy paintbrush - Joe - 1 hr
5.1.5. buy screwdriver - Joe - 1 hr
5.2. Materials - Billy - 7 hrs
5.2.1. buy Wood - Billy - 1 hr
5.2.2. buy Screws - Billy - 1 hr
5.2.3. buy Picture Hanger - Billy - 1 hr
5.2.4. buy Paint - Billy - 1 hr
5.2.5. buy wood stain - Billy - 1 hr
5.2.6. buy trim - Billy - 1 hr
5.2.7. buy cleaning supplies - Billy - 1 hr
6. Finishing touches (Joe 9 hrs)
6.1. Paint - Joe - 4 hrs
6.1.1. Paint Walls - Joe - 1 hr
6.1.2. Paint Roof - Joe - 1 hr
6.1.3. Paint Floor - Joe - 1 hr
6.1.4. Paint Door - Joe - 1 hr
6.2. Clean - Joe - 3 hrs
6.2.1. sweep floors - Joe - 1 hr
6.2.2. mop floors - Joe - 1 hr
6.2.3. dust - Joe - 1 hr
6.3. Giant red bow - Billy - 2 hrs
6.3.1. buy red bow - Billy - 1 hr
6.3.2. hang red bow on roof - Billy - 1 hr
7. Preliminary measures (Joe 3 hrs)
7.1. project approval - Joe - 1 hr
7.1.1. bring work breakdown to client - Joe - 1 hr
7.2. dog measurements - Joe - 2 hrs
7.2.1. measure dog - Joe - 1 hr
7.2.2. record measurements - Joe - 1 hr