1. 1. Site Mobilization

1.1. 1.1. Preliminaries

1.1.1. Site Office Setup

1.1.2. Temporary Electricity,Water and Drainage Connection

1.1.3. Erection of tower crane

1.2. 1.2 Site Formation

1.2.1. Site possession

1.2.2. Transplant of existing trees

2. 2. Structural Works

2.1. 2.1. RC Frames

2.1.1. RC structure

2.2. 2.2. Substructure

2.2.1. Construction of basement level

2.2.2. Underground drainage system

2.3. 2.3. Excavation

3. 3. Internal Finishing

3.1. Installation of material hoist

3.2. Wall plastering

3.3. Installation of doors and windows

4. 4. External Finishing

4.1. Erection of Gondolas or Scaffolding

4.2. Curtain work/Cladding work

4.3. Painter (Base Coat)

4.4. Painter (Final Coat)

5. 5. Building Services

5.1. 5.1 Water Services

5.1.1. Plumbing and aboveground drainage

5.1.1.1. Connection to Last Manhole

5.2. 5.2 Electricity Services

5.2.1. Installation of Tx room

5.2.2. Power energization

5.3. 5.3 Air conditioning Services

5.3.1. MVAC installation

5.4. 5.4 Lift Installation

5.4.1. Lift installation

5.5. 5.5 Fire Services Installation

5.5.1. FS water installation

5.5.2. FS installation

6. 6. Inspection and Handover

6.1. Fitting out works

6.2. Cleaning of pavement