Fluffy 作者: Mind Map: Fluffy

1. Materials

1.1. Plywood

1.1.1. 10 at $40 = $400

1.2. 2x4s

1.2.1. 40 at $7.50 = $300

1.3. Paint/Primer

1.3.1. $150

1.4. Shingles

1.4.1. 3 bundles at $30 = $90

1.5. Nail Gun

1.5.1. 1 week rental = $80

1.6. Compressor

1.6.1. 1 week rental = $132

1.7. Nails

1.7.1. $50

1.8. Concrete

1.8.1. 24 bags @ $4 = $96

1.9. Cement Mixer

1.9.1. 1 week rental = $192

1.10. Insulation

1.10.1. 8 bags = $410

1.11. Carpet

1.11.1. $0.60x 32 sq ft = $20

1.12. Windows

1.12.1. 2 at $20 = $40

2. Costs

2.1. $5000

2.1.1. Labor: 40%

2.1.1.1. $2000

2.1.2. Materials: 40%

2.1.2.1. $2000

2.1.3. Profit: 15%

2.1.3.1. $750

2.1.4. Unexpected: 5%

2.1.4.1. $250

3. Dimensions

3.1. Base

3.1.1. 4x8

3.2. Roof

3.2.1. 3x8

3.3. Door

3.3.1. 4x3

3.4. Windows

3.4.1. 1x1

4. Plan/Tasks

4.1. Day 1

4.1.1. Construct Slab

4.1.2. Mix and pour concrete

4.2. Day 2

4.2.1. Construct Frame

4.2.2. Put up walls

4.2.3. cut out door

4.3. Day 3

4.3.1. Build roof

4.3.2. Cut shingles

4.3.3. Nail down shingles

4.4. Day 4

4.4.1. Insulate walls

4.4.2. Paint outside and inside walls

4.5. Day 5

4.5.1. Cut carpeting

4.5.2. Lay down carpeting

4.5.3. Clean up yard

4.6. Day 6

4.6.1. Recieve Payment

4.6.2. Recieve Feedback

5. Employees

5.1. Superivsor

5.2. Contractor/roofer

5.3. Painter

6. Deliverables

6.1. Large structure w/ Roof

6.2. Insulated Walls

6.3. Windows

6.4. Concrete Slab

6.5. Detailed Interior

6.6. Finished Structure

6.7. Client Meeting