WORK BREAKDOWN STRUCTURE CLUSTER GALEA TIPE 43/VARIABEL

Get Started. It's Free
or sign up with your email address
Rocket clouds
WORK BREAKDOWN STRUCTURE CLUSTER GALEA TIPE 43/VARIABEL by Mind Map: WORK BREAKDOWN STRUCTURE CLUSTER GALEA TIPE 43/VARIABEL

1. 1. PEK. PENDAHULUAN

1.1. PEMBERSIHAN TANAH

1.2. PEK. LISTRIK KERJA

1.2.1. Pemasangan Listrik PLN 2300 W

1.3. PEKERJAAN AIR

1.3.1. Pembuatan Sumur

1.3.2. Pembelian Jetpam

1.4. PEMASANGAN BOWPLANK

1.4.1. KAYU MERANTI 2 X 20 X 4 m

1.5. PEMBUATAN BEDENG

1.5.1. DINDING PLAYWOOD 3,5 X 2,5 m Ketebalan 4 mm

1.5.2. ATAP SENG GELOMBANG BJLS 32 4 X 3 m

2. 3. PEK. STRUKTUR

2.1. SLOOF 15 X 15 m

2.1.1. PEMBESIAN

2.1.2. BEKISTING

2.1.3. PENGECORAN BETON

2.2. KOLOM 20 X 20 m

2.3. RING BALOK 15 X 15 m

2.4. SOPI-SOPI 15 X 15 m

3. 2. PEK. TANAH DAN PONDASI

3.1. PEK. GALIAN TANAH

3.1.1. PEK. GALIAN PONDASI

3.1.2. PEK. GALIAN SEPTIC TANK

3.1.3. PEK. AIR TANAH

3.1.4. PEK. PEMBUANGAN TANAH

3.1.5. PEK. BAK KONTROL

3.1.6. PEK. GALIAN RESAPAN

3.2. PEK. PONDASI

3.2.1. PEK. URUGAN PASIR BAWAH

3.2.2. PEK. PEMASANGAN ANSTAMPING

3.2.3. PEK. PEMASANGAN BATU KALI

3.2.4. PEK. URUGAN TANAH KEMBALI

3.2.5. PEK. PEMADATAN TANAH

4. 4. PEK. MEP

4.1. PEK. PLUMBING

4.1.1. PEK. AIR BERSIH

4.1.1.1. Standard PDAM

4.1.1.2. Pek. Pipa PVC 3"

4.1.1.3. Pek. Kran Air

4.1.1.4. Pek. Shower

4.1.2. PEK. AIR KOTOR

4.1.2.1. Pek. Pipa PVC 4"

4.1.2.2. Pek. Floor Drain

4.1.2.3. Pek. Kloset

4.1.2.4. Pek. Wastafel

4.1.2.5. Pek. Septic Tank

4.1.2.6. Pek. Bak Kontrol

4.1.2.7. Pek. Resapan

4.2. PEK. ELECTRICAL

4.2.1. Pek. Pemasangan panel box dan sekring

4.2.2. Pek. Titik Lampu

4.2.3. Pek. Saklar

4.2.4. Pek. Stop kontak

4.2.5. Pek. Tarikan Kabel

4.3. PEK. MECHANICAL

4.3.1. PEMASANGAN MESIN AIR

4.3.2. PEMASANGAN AC

5. 5. PEK. ARSITEKTUR

5.1. PEK. DINDING

5.1.1. PEMASANGAN PASANGAN DINDING

5.1.1.1. Pasangan Dinding 1 ; 3 (kamar mandi)

5.1.1.2. Pasangan Dinding 1 ; 5 (dinding luar)

5.1.1.3. Pasangan Dinding 1 ; 5 (sopi-sopi)

5.1.2. Plesteran keseluruhan

5.1.3. Acian keseluruhan

5.2. PEK. TRASRAM BATA 1:2

5.2.1. Pemasangan Bata

5.2.2. Plester

5.2.3. Acian

5.3. PEK. PINTU DAN JENDELA

5.3.1. PEK. PINTU

5.3.1.1. DAUN PINTU UTAMA (LAMINATED DOOR)

5.3.1.2. DAUN PINTU KAMAR (MDF RANGKA LVL)

5.3.1.3. DAUN [PINTU KM/WC (PVC)

5.3.1.4. DAUN PINTU DAPUR (MDF RANGKA LVL)

5.3.1.5. KUSEN KAYU (KAYU BORNEO)

5.3.1.6. ENGSEL

5.3.1.7. HANDLE DAN KUNCI

5.3.2. PEK. JENDELA

5.3.2.1. 1 SET/UNIT JENDELA KAYU BORNEO

5.4. PEMASANGAN KERAMIK

5.4.1. URUGAN PASIR BAWAH LANTAI

5.4.2. LANTAI KERJA

5.4.3. PEK. KERAMIK LANTAI

5.5. PEK. ATAP

5.5.1. PEKERJAAN RANGKA ATAP

5.5.2. PEK. PLAFOND GYPSUM

5.5.3. PEK. LIST PLAFOND

6. 6. PEK FINISHING

6.1. CAT DINDING INTERIOR DAN EKSTERIOR

6.2. PENGECATAN KUSEN, DAUN PINTU, PLAFOND, LIST PLAFOND

6.3. PENYEDIAAN PENEMPATAN AC

6.4. PEK. CAR PORT

6.5. PEMASANGAN KITCHEN SET