PMP - Values da Mind Map: PMP - Values

1. Present values

1.1. PV = FV / (1+i)ˆt

1.2. NPV = ∑ PV(t) - Initial investment

2. Returns

2.1. ROI = (Benefit - Cost) / Cost

2.2. ROIC = Net income after tax / capital invested

3. Expected monetary value

3.1. EMV = % * I

4. Channels

4.1. Ch = n * (n-1) / 2

5. Slacks

5.1. EF = ES + d - 1

5.2. LF = LS + d - 1

5.3. F = LS - ES

5.4. F = LF - EF

6. Bases

6.1. BAC = Budget at completion

6.2. AC = Actual cost

7. Values

7.1. EV = Earned % * BAC

7.2. PV = Planned % * BAC

8. Variances

8.1. CV = EV - AC

8.2. SV = EV - PV

9. Ratio

9.1. CPI = EV / AC

9.2. SPI = EV / PV

10. At completion

10.1. EAC = BAC / CPI

10.2. ETC = EAC - AC

10.3. VAC = BAC - AC

10.4. TCPI = (BAC-EV) / remaining funds