Pedestrian Bridge Project Bekasi

Kom i gang. Det er Gratis
eller tilmeld med din email adresse
Pedestrian Bridge Project Bekasi af Mind Map: Pedestrian Bridge Project Bekasi

1. General Works

1.1. Surveying

1.1.1. Measuring the construction site

1.1.2. Installing the project boundaries

1.2. Land Clearing

1.2.1. Clearing site from vegetation

1.2.2. Clearing site from buldings/structures

1.2.3. Clearing site from trashes

1.3. Soil Tests

1.3.1. Conducting SPT and hand boring tests

1.3.2. Conducting CPT test

1.4. Temporary Facilities

1.4.1. Installing project information board

1.4.2. Installing boundary fence around the project

1.4.3. Preparing fabrication area and stockyard area

1.4.4. Construction project's temporary office

1.4.5. Electricity

1.4.6. Temporary Water Provision

1.4.7. Roadsigns installation

1.4.8. HSE equipments

1.4.9. Toilet

1.5. Material and Equipments Mobilisation

1.5.1. Materials Procurement

1.5.2. Equipments procurement

2. Utilities and Finishing Works

2.1. Finishing Works

2.1.1. Railing installation

2.1.2. Polycarbonate roof installation

2.1.3. Pengamplasan dan Pembersihan Karat

2.1.4. Painting

2.2. Utilities

2.2.1. Electrical cable installation

2.2.2. Lighting installation

2.3. Restoration

2.3.1. Plantation and vegetation restoration

2.3.2. Sidewalk reparation

2.4. Demobilisation

3. Sub-Structure Works

3.1. Spun Pile Foundation

3.1.1. Location Marking

3.1.2. Pile Platform preparation

3.1.3. Pile driver equipment mobilisation

3.1.4. Spun Pile mobilisation

3.1.5. Verticality Check

3.1.6. Spun pile installation

3.2. Footing Foundation

3.2.1. Marking

3.2.2. Excavation for foundation

3.2.3. Compaction for foundation

3.2.4. Soil filling works

3.2.5. Soil disposal works from excavation

3.2.6. Formwork Installation

3.2.7. Reinforcement bar installation

3.2.8. Concrete casting for foundation

3.2.9. Concrete Curing and pelepasan bekisting

3.3. Pile Cap

3.3.1. Marking

3.3.2. Excavation for pile cap

3.3.3. Soil disposal

3.3.4. Spun pile cutting

3.3.5. Formwork installation

3.3.6. Reinforcement bar fabrication

3.3.7. Reinforcement bar installation

3.3.8. Concrete casting for foundation

3.3.9. Concrete Curing and pelepasan bekisting

3.3.10. Disposal Mobilization

3.4. Pedestal of Column

3.4.1. Column pedestal reinforcement bar installation

3.4.2. Base plate installation

3.4.3. Formwork installation

3.4.4. Concrete casting for pedestal

3.4.5. Angkur

4. Upper Structure Works

4.1. Column

4.1.1. Stiffener installation

4.1.2. Column to base plate installation

4.1.3. Connection works of column

4.2. Beam in Main Structure

4.2.1. Connection works for girder-beam

4.2.2. Beam lifting

4.2.3. Beam Cutting

4.2.4. Conection works girder-girder

4.2.5. Connection works main girder-stair girder

4.2.6. Connection works girder-column

4.3. Beam in Stair Structure

4.3.1. Beam Procurement and Mobilisation (Beam cutting and fabrication bisa di subkon eg morinda, bukaka, wijaya karya)

4.3.2. Beam lifting (cari alatnya)

4.3.3. Connection works for girder-beam

4.3.4. Connection works girder-girder

4.3.5. Connection works girder-column

4.4. Floor Plate

4.4.1. Plate Procurement and Mobilisation (cari subcon)

4.4.2. Plate installation for main structure

4.4.3. Plate installation for stair structure

4.5. Roof system

4.5.1. Roof support installlation

4.5.2. Roof frame installation

4.5.3. Roof connection works