Land research

Comienza Ya. Es Gratis
ó regístrate con tu dirección de correo electrónico
Land research por Mind Map: Land research

1. Heda

1.1. Requirements

1.1.1. Plot ratio more than 1.6

1.1.1.1. Warehouse

1.1.1.1.1. How do we count the pallet rack level

1.1.1.2. Pfizer example. Do they comply?

1.1.2. 127,5 million RMB / hectare (16mEur)

1.1.2.1. 3 years after construction start

1.1.2.1.1. This rule is not strictly implemented

1.2. Subsidizes

1.2.1. To be completed

1.3. Land option 1

1.3.1. Address

1.3.2. 20min from Ebvac

1.3.3. 2km north of Double Tree (Jinshahu station)

1.3.4. Accessible by bus

1.3.5. Name: Pharmaceuticals village

1.3.6. No push-back with 400 pigs on site

1.4. Buying process

1.4.1. 1. Ceva provides to Heda project report

1.4.1.1. Ebvac Master Plan

1.4.1.1.1. Poultry future

1.4.2. 2. Negociation with Heda

1.4.3. 3. Heda decision meeting

1.4.4. 4. Application process to acquire the land

1.4.4.1. 3-6 months

1.5. Land option 2

2. Scope

2.1. QC animal house

2.2. R&D center

2.2.1. R&D labs

2.2.1.1. Limited activities

2.2.2. Animal house

2.3. Warehouse

2.3.1. Can we have a warehouse out of production site for raw materials and finished products ?

2.3.2. Define the warehouse needs

3. Site master plan

3.1. Input

3.1.1. R&D

3.1.2. Country / business

3.1.3. Industrial

3.2. Suppliers

3.2.1. Technip

3.2.2. NNE

3.2.3. Foster wheeler

4. Candidates for land research support

4.1. SIP

4.2. GSE

4.3. Jones Langlasalle

4.4. PM group

5. Permitting

5.1. Document needed

5.1.1. Environmental Impact Assessment

5.1.1.1. Lead time 9 months

5.1.1.1.1. 6 months report preparation

5.1.1.1.2. 3 months bureau review

5.1.1.2. Not required for construction permit

5.1.1.3. Need concept design

5.1.1.4. Do not need land purchase done

5.1.2. Approval for project registration

5.1.3. Construction permit

5.1.3.1. Soil survey

5.1.3.2. Planning permit

5.1.3.2.1. Preliminary design approval

5.1.3.2.2. Lead time: 3 months after concept design

5.1.3.3. Detailed design third party review

5.1.3.3.1. Lead time: 2 months

6. Working team

6.1. QA

6.2. QC

6.3. Warehouse

6.4. Engineering

6.5. R&D