HDD WORK Scheduled to Start on 13/01/2020

Kom i gang. Det er Gratis
eller tilmeld med din email adresse
HDD WORK Scheduled to Start on 13/01/2020 af Mind Map: HDD WORK Scheduled to Start on  13/01/2020

1. Resorces

1.1. Accessores

1.1.1. Inter Connection Water Hose

1.1.2. Hand Tools

1.1.3. Welding Machine

1.2. Disel

1.2.1. HDD Machine 300 ltr

1.2.2. Mud Pump 120 ltr

1.2.3. DG 120 ltr

1.2.4. Excavator & Hydra 150 ltr

1.2.5. Water Supply 100 ltr

1.2.6. Back Rod Transportation 60 ltr

1.3. Project Manager

1.3.1. Site Staffs & Labours

1.3.1.1. Administration

1.3.1.1.1. Store & Purchase

1.3.1.1.2. Accounts & Cash

1.3.1.2. Techinical

1.3.1.2.1. Site Sup -2

1.3.1.2.2. Machine Oprator -1

1.3.1.2.3. Traker -1

1.3.1.2.4. Driver -3

1.3.1.3. Labours

1.3.1.3.1. Mixing Plant Opration -3

1.3.1.3.2. Machine and Crean -2

1.3.1.3.3. Hydra & Exca -2

1.3.1.3.4. Mud Pump -1

1.3.1.3.5. Exit Side after Pilot -4

1.3.1.3.6. Cokking Team for Lac -2

1.3.1.3.7. Cokking Team for Sta -2

1.3.1.3.8. Water Pump Handling-2

2. Project-1 Plant & Machinerys

2.1. 100 XCMG With 90 No Drill Rods

2.1.1. Mud Pump 300 G{M

2.1.2. Mud Motor With Trycone Bit 165 mm

2.1.3. Mud Mixing Unit

2.1.4. Recycling Plant

2.1.5. DG 150 kva

2.1.6. Excavator & Hydra

2.1.7. Water Tanker Lorry For Water Supply - 2 Nos

2.1.8. Water Pump With Motor or Engine - 2 Nos

2.1.9. Pic-up Truck or Tata Ace fot labour tranportation & Disel, other purchase

2.1.10. Lorry with ramp for back rod transportation