Fibre Order Changes

Iniziamo. È gratuito!
o registrati con il tuo indirizzo email
Fibre Order Changes da Mind Map: Fibre Order Changes

1. NBN initiated

1.1. change of address or POI (point of Interconnect)?

1.1.1. Has build started ?

1.1.1.1. Yes

1.1.1.1.1. Cancel original order with reason code (new address)

1.1.1.2. No

1.1.1.2.1. Design team completes modifications

2. InfraCo initiated

2.1. SDP location or Fibre tail location changed

2.1.1. Notify NBN asap