T-REX concept phase

Laten we beginnen. Het is Gratis
of registreren met je e-mailadres
T-REX concept phase Door Mind Map: T-REX concept phase

1. Cabinet FF

1.1. Producibility of liner

1.1.1. Contact with AKAplast (week 33)

1.2. Deformation of foamed cabinet (time + produce)

1.3. Variable width tooling not in place yet

1.4. Wrapper construction not defined yet

1.5. Condensation appearing on outside module?

2. Cabinet FR

2.1. Producibility of liner

2.2. Deformation of foamed cabinet (time + produce)

2.3. Variable width tooling not in place yet

2.4. Wrapper construction not defined yet

2.5. Condensation appearing on outside module?

3. CU housing

3.1. Used material not suitabel for T-REX 1, new concept to be made

3.2. Implement proper interface in newly chosen material/technique

4. Interface between modules

4.1. Concept for routing to be made

4.1.1. foamed concept

4.1.2. armaflex concept

4.1.3. positioning in tool concept

4.2. Robustness of concept to be guaranteed

4.3. Line out between modules to be constant

4.4. No condens should appear on outside of fridge (especially near piping

5. Lighting

5.1. Foamtightness to be guaranteed

5.2. Condensation appearing on outside module? adapting lighting housing design

5.3. Functioning of lighting to be user tested

5.3.1. positioning of lighting to be tested (detail design)

5.4. Change according to impact on interior setup

6. User interface

6.1. Performance of lighting

7. Production process

7.1. Process is leading

7.2. How to deal with high variaty in width?

7.3. How to deal with incoming parts in different width?

8. Door FF+FR

8.1. Gasket performance not verified

8.2. Gasket does not close

8.3. Foam panel supplier not chosen

8.4. Logistics of foam panels not yet clearified

8.5. Closing mechanism pulls the drawer also when there is obstacle in the way

8.6. When something tall is in the interior bin it will scrape/touch the cabinet ceiling

8.7. force by closing system is too much for user to handle (40N)

9. Fan housing 50%

9.1. Fan housing buildt (construction)

9.1.1. CAD files ready

9.2. Fan housing verified on airflow inside

9.2.1. Airflow measurement of drawn housing

9.3. Fan housing verified on airflow outside

9.4. Fan housing verified on airflow direction

10. Cooling system

10.1. Performance not yet verified

10.1.1. 1. Performance cooling system alone

10.1.2. 2. Performance cooling system in cabinet with airflow

10.1.3. 3. Performance cooling system in cabinet + airflow + door

10.1.4. 4. Performance cooling system in cabinet + airlfow + door + interior

10.2. Parts not completely sourced yet

10.2.1. evaporator (Drawing to be send)

10.2.2. fans (To be verfified)

10.2.3. Heater (To be drawn)

10.2.4. reed switch (To be verified)

10.2.5. temp sensor (To be verified

11. Locking

11.1. Closing mechanism not yet choosen

11.1.1. Drawer guide verficiation + forces spring mechanism

11.2. Panel attachement not yet defined

11.2.1. Choose Hymer supplied config or mix

11.3. Winterlock to be added

12. Drawer FF

12.1. When something tall is in the interior bin it will scrape/touch the cabinet ceiling

12.1.1. Solution needed

12.2. Variable width tooling not in place yet

12.3. Airflow through drawer + interior to be verified

13. Drawer FR

13.1. When something tall is in the interior bin it will scrape/touch the cabinet ceiling

13.1.1. Solution needed

14. electronics

14.1. CI-bus protocol and parameters ready

14.2. Cooling algorithm ready

15. Interior

15.1. When something high is in the interior bin it will touch the cabinet ceiling and put pressure on the interior construction

15.1.1. Solution needed

15.2. Positioning on variable width tub

15.3. Tolerance risk to be solved (parallelism)

15.4. Robustness of design (fool proof)

15.5. User experience testing and applying of the changes.

15.6. Is interior influencing lighting of cabinet?