1.0 HOUSE by Mind Map: 1.0 HOUSE

1. 1.1 Preparation

1.1. 1.1.1 Hire construction team

1.1.1. 1.1.1.1 Sign a contract with construction company

1.2. 1.1.2 Organize the kick of meeting with Sponsor, Architect and Foreman

1.3. 1.1.3 Rent equipment

1.3.1. 1.1.3.1 Sign a contract with company

1.3.1.1. 1.1.3.2 Deliver equipment

1.4. 1.1.4 Receive building permits

1.4.1. 1.1.4.1 Apply for the building permits

1.5. 1.1.5 Procure materials

1.5.1. 1.1.5.1 Prepare a list of necessary materials

1.5.1.1. 1.1.5.2 Order materials

1.5.1.1.1. 1.1.5.3 Receive materials

2. 1.2 Foundation

2.1. 1.2.1 Examine the soil

2.1.1. 1.2.1.1 Measure ground elevation

2.1.1.1. 1.2.1.2 Measure soil resistivity

2.2. 1.2.2 Excavate foundation

2.2.1. 1.2.2.1 Inspect the ground

2.2.1.1. 1.2.2.2 Excavate

2.3. 1.2.3 Pour foundation

2.3.1. 1.2.3.1 Prepare the cement

2.3.1.1. 1.2.3.2 Pour the foundation

2.3.1.1.1. 1.2.3.3 Dried up the foundation

2.4. 1.2.4 Block construction

2.4.1. 1.2.4.1 Build the rods carcass

2.4.1.1. 1.2.4.2 Build wooden carcass

2.4.1.1.1. 1.2.4.3 Pour cement blocks

2.4.2. 1.2.2 Approve codes permitl

2.4.2.1. 1.2.2.1Apply for the permits

2.4.2.1.1. 1.2.2.2 Organize permits approval meeting

2.4.2.2. 1.2.3 Landscaping

2.4.2.2.1. 1.2.3.1 Construct driveway

2.4.2.2.2. 1.2.3.2 Shield the backyard space

3. 1.5 Framework

3.1. 1.5.1 Install Sheetrock

3.1.1. 1.5.1.1 Receive materials

3.1.1.1. 1.5.1.1 Install sheetrock

3.2. 1.5.2 Construct roof

3.2.1. 1.5.2.1 Receive frame materials

3.2.1.1. 1.5.2.2 Construct wooden roof carcass

3.2.1.1.1. 1.5.2.3 Cover the roof

3.3. 1.5.3 Install Doors

3.3.1. 1.5.3.1 Receive materials

3.3.1.1. 1.5.3.2 Adjust doorway

3.3.1.1.1. Install doors

3.4. 1.5.4 Install Windows

3.4.1. 1.5.4.1 Receive materials

3.4.1.1. 1.5.4.2 Adjust windows aperture

3.4.1.1.1. 1.5.4.3 Install windows

3.5. 1.5.5 Flooring

3.5.1. 1.5.5.1 Receive materials

3.5.1.1. 1.5.5.2 Prepare floor foundation

3.5.1.1.1. 1.5.5.3 Cover the floor

3.6. 1.5.6 Insulate walls

3.6.1. 1.5.6.1 Receive materials

3.6.1.1. 1.5.6.2 Install insulation

3.6.1.1.1. 1.5.6.3 Test insulation

3.7. 1.5.7 Install celling

3.7.1. 1.5.7.1 Receive materials

3.7.2. 1.5.7.2 Install heating system above ceiling line

3.7.2.1. 1.5.7.3 Construct celling

4. 1.4 Plumbing

4.1. 1.4.1 Install water pipes

4.1.1. 1.4.1.1 Receive materials

4.1.2. 1.4.1.2 Connect pipes with the central water system

4.1.2.1. 1.4.1.3 Test water system

4.2. 1.4.2 Install canalization pipes

4.2.1. 1.4.2.1 Connect canalization pipes with central canalization system

4.2.1.1. 1.4.2.2 Test canalization system

5. 1.6 Electricity

5.1. 1.6.1 Install wiring system

5.1.1. 1.6.1.1 Receive materials

5.1.1.1. 1.6.1.2 Cabling indoor

5.1.1.1.1. 1.6.1.2 Cabling outdoor

6. 1.8 Interior Design

6.1. 1.8.1 Paint the walls

6.2. 1.8.1.1 Receive materials

6.2.1. 1.8.1.2 Paint the walls

6.2.1.1. 1.8.1.3 Dried up the walls

6.3. 1.8.2 Clean the house

6.4. 1.7.3 Backyard fencing

6.4.1. 1.7.3.1 Receive materials

6.4.1.1. 1.7.3.2 Fence the backyard

7. 1.9 Closing

7.1. 1.9.1 Return equipment

7.2. 1.9.1 Clean the house area

7.3. 1.9.2 Sign off documents with contractor