1. Construction - Sarah (12 hrs)
1.1. Labor (Sarah 4 hr)
1.1.1. determine construction schedule - Sarah
1.1.2. agree to labor payments - Sarah
1.2. Roof (Jason 2 hrs)
1.2.1. frame roof
1.2.2. insulate roof
1.2.3. shingle roof
1.3. House (Jason 3 hrs)
1.3.1. frame house
1.3.2. insulate house
1.3.3. install windows
1.3.4. install doors
1.3.5. install roof
1.4. Concrete Pad (Sarah 3 hrs)
1.4.1. pour concrete
1.4.2. paint concrete
2. Client Evaluation (Jason 9 hrs)
2.1. Dog Meeting (Jason 3 hrs)
2.1.1. take measurements of Fluffy - Sarah -1
2.1.2. determine use of dog house - Jason - 2
2.2. Budget (Jason 6 hrs)
2.2.1. solidify labor costs - Sarah - 3
2.2.2. solidify material budget - Sarah - 2
2.2.3. agree to payment schedule - Jason -1
3. Design (Sarah 2 hrs)
3.1. Work-site evaluation (Sarah 1 hr)
3.1.1. Take space measurements
3.1.2. Evaluate any space limitations
3.2. Blueprint (Jason 1 hr)
3.2.1. design house
3.2.2. meet with client to ok house design
4. Finishing (Jason 5 hrs)
4.1. House (Jason 4 hrs)
4.1.1. paint house
4.1.2. install water bowl
4.1.3. install dog bed
4.1.4. paint windows
4.1.5. paint doors
4.2. Final Approvals (Sarah 1 hr)
4.2.1. client inspection
4.2.2. final payments collected