AET - Data Center Migration Project Planning
by Jason Curry
1. Network Design and Management
1.1. Figure out how to and design network (14 days)
1.1.1. Order New Ventilation System, Racks, and Power supplies (21 days for delivery)
1.1.1.1. Install New Ventilation System (7 Days)
1.1.1.2. Install New Racks (21 Days)
1.1.1.2.1. Run New Data Cables (7 Days)
1.1.1.2.2. Install Power Supplies (5 Days)
1.1.2. Meet With Functional Leaders for Switch Over Approval (28 Days)
2. Renovating Data Center
2.1. Screen and Hire new workers (7 Days)
2.1.1. Data Center Construction (20 Days)
2.1.1.1. Inspector to Approve Construction (2 Days)