Installation Milestones
by James Arthur
1. Milestone 1 - Design
1.1. Scope
1.1.1. Resources
1.1.1.1. Materials
1.1.1.2. Budget 7/12
1.1.2. Project Goal(s)
1.1.3. Deadlines
2. Milestone 2 - Build
2.1. Aquire Materials
2.1.1. Prototype Materials must be delivered to Shawn by 7/15
2.1.2. Bamboo, Remaining Cube, hardware and electronics due by 7/18
2.2. Cube Prototype Built 7/18
2.3. Programming
2.3.1. Computer and/or Arduino Setup
2.3.2. Connector and Adapters
2.4. Project Built 7/25
2.4.1. 64 Completed Partially Cubes 7/25
2.4.2. Bamboo Structure 7/24
2.4.2.1. Bamboo Support Labor
2.4.3. Assemble Cubes
2.4.3.1. Install LED into Cube
2.4.4. Wire Cubes
2.4.5. Connect Cubes
2.5. Project Tested 7/25
3. Milestone 3 - Installation
3.1. Labor
3.1.1. Installation
3.1.2. 1 Support Person
3.1.3. On Site Testing
3.2. Delievery
3.3. Power
3.4. Barricades
4. Milestone 4 - Strike
4.1. Labor
4.1.1. Breakdown